m²
cm
cm
%

Standard 5% – for circular patterns or herringbone laying, plan for up to 10%.

Sub-base: excavation, base course, beddingbedding 4 cm · base course 20 cm
cm
cm

Assumption 4 cm compacted (typically 3–5 cm)

cm

Assumption 20 cm – more for driveways; the contractor sets the thickness based on use and soil

%

Loose delivery volume vs. compacted layer – assumption 25%

t/m³
t/m³

Stones needed

1,050pieces

1,050

For 20 m² you need 1,050 stones of 10 × 20 cm: 1,000 for the area and 50 as wastage (5%).

20 m²
Area shown as a square, stones to scale in a running bond
  • Area1,000 pcs95%
  • Wastage50 pcs5%
Area per stone
0.02 m²

Sub-base: excavation, base course, bedding

Excavation (paver + bedding + base course)
6.4 m³
Crushed stone for 20 cm base course4 m³ compacted
5 m³ · 9 t
Grit for 4 cm bedding0.8 m³ compacted
1 m³ · 1.5 t

Quantities from area × layer thickness; allowance and bulk densities are assumptions – the delivery note and the design take precedence.

How this was calculated
A_S = 0.1 m × 0.2 m = 0.02 m²
n = ⌈20 ÷ 0.02 × (1 + 5 %)⌉ = 1,050

Order all stones from a single delivery. Colour batches can vary slightly and may be visible side by side.

Paving Stone Calculator by Rechnerzentrale(opens in a new tab)